Mechanic's lien · Los Angeles, CA

Mechanic's lien in Los Angeles, CA

In Los Angeles, contractors must serve a Preliminary Notice within 20 days of first furnishing labor or materials (Civ. Code § 8800) to preserve mechanic's lien rights. The notice must be sent to the property owner and construction lender via certified mail.

Governing statutes

Cal. Civ. Code § 8800Cal. Civ. Code § 8400Cal. Civ. Code § 8410Cal. CCP § 338

20

days for many preliminary notices (§ 8800)

90

days to record the lien after completion

$29.99

one-off, preview free

The process in Los Angeles

  1. 1

    Serve Preliminary Notice

    Within 20 days of first furnishing labor or materials, serve a Preliminary Notice per Civ. Code § 8800(f). Send via certified mail to the owner, general contractor, and construction lender.

  2. 2

    Record Mechanic's Lien

    If unpaid, record a Mechanic's Lien with the LA County Recorder within 90 days of completion or 60 days after notice of completion, whichever is earlier (Civ. Code § 8410).

  3. 3

    File Lien Foreclosure

    File a lawsuit to foreclose the mechanic's lien within 90 days of recording. The LA County Superior Court handles lien foreclosure cases.

Los Angeles filing details

Processing time: 2-3 weeks for case assignment Confirm the current fee on the court's published schedule before you file — amounts change.

Where a lien is recorded

LA County Registrar-Recorder / County Clerk

12400 Imperial Hwy, Norwalk, CA 90650

Where it is filed

Los Angeles Superior Court — Stanley Mosk Courthouse

111 N Hill St, Los Angeles, CA 90012

Documents on this track

Each one is drafted to the citations above — preview free, unlock as a court-ready PDF.

  • Preliminary NoticeCiv. § 8800(f)
  • Mechanic's LienCiv. § 8400
  • Demand LetterPre-lien demand

Questions people ask about Los Angeles

What is the deadline for preliminary notice in LA?+

Contractors must serve a Preliminary Notice within 20 days of first furnishing labor or materials (Civ. Code § 8800). Missing this deadline forfeits lien rights for all work performed before the late notice is served.

How much does it cost to file a mechanic's lien in LA County?+

Recording fees at the LA County Recorder are approximately $14 for the first page and $3 per additional page. The foreclosure lawsuit filing fee at LA Superior Court is $225.

Also in this jurisdiction: Eviction notice (Los Angeles) · Eviction notice (San Diego)

Draft the Los Angeles notice today

Guided facts, live statute retrieval, full preview before you pay. $29.99 one-off — or $10 a document on Pro.